As per Test Case 1, selection of the appropriate cell resolution during a real-world project requires consideration of the intended use of the results and also how the simulation run time impacts the overall project timeline.
* Detailed integrated
* Broad-scale quick run simulation for urban flood forecasting purposes may adopt a coarser 20ft cell resolution or investigate the suitability of a 25ft cell resolution to achieve a quicker simulation turnaround time.
| |||