Line 212:
After the conversion is complete it is important to check the output. Some key areas to check are:
* The 1d_nwk.mif file appears to have created channels at reasonable locations
* The 1d_nwk.mif ‘Type’ attribute is correct (currently the utility will assign all channels to type ‘S’ (see below for checking for culverts in MIKE11))
* The 1d_xs.mif file appears to be at reasonable locations (if the cross sections in MIKE11 didn’t have X,Y coordinates, then the equivalent 1d_xs cross sections can look strange)
** TUFLOW also does not require cross sections at embedded 1D/2D culverts, therefore cross sections at these locations can be deleted