Tutorial M02 001 GIS Inputs QGIS: Difference between revisions

Content deleted Content added
No edit summary
 
(4 intermediate revisions by the same user not shown)
Line 11:
<li>Click 'OK' and save the QGIS workspace by selecting Project > Save As.<br>
<br>
[[File:M02 Configure Project v3M02_SHP_ConfigureProject.pngPNG]]<br><br>
<li>Set the QGIS workspace projection to EPSG:32760, see <u>[https://wiki.tuflow.com/index.php?title=Tutorial_Site_Familiarisation_QGIS#Set_the_Projection Set the Projection]</u>.
</ol>
Line 18:
= Method =
Navigate to the '''Module_02\Tutorial_Data''' folder. Copy the below GIS files into the '''Module_02\TUFLOW\model\gis''' folder:
:*'''2d_zsh_M02_rd_crest_001_L'''
:*'''2d_zsh_M02_rd_crest_001_P'''
 
Investigate the supplied files:
Line 31:
:*The Shape_Option of 'MAX' is specified for all breaklines. The Zpt elevations only changes when the Z shape elevation at the Zpt is higher. The purpose of the Z shape is to enforce the highest elevations along the road crest.
<br>
{{Video|name=Animation_M02_GIS_001_01_.mp4|width=1279}}<br>
[[File:Animation M02 GIS 001 01.gif]]<br>
<br>
<li>The 2d_zsh point layer is used to apply elevation to the breaklines:
:*The values in the 'Z' attribute are elevations above datum assigned to each point. The elevations are being interpolated along the breakline.
:*The points must be snapped to the vertices of the 2d_zsh line to instruct TUFLOW that these layers are linked. If no points are in the layer, the elevation on the line object is used, i.e. the elevation along the line does not vary. For more information, seerefer Table 6-8 ofto the <u>[https://downloadsdocs.tuflow.com/_archiveclassic-hpc/TUFLOWmanual/Releaseslatest/2018-03/TUFLOW%20Manual.2018-03.pdf 2018 TUFLOW Manual]</u>.
<br>
{{Video|name=Animation_M02_GIS_001_02.mp4|width=1279}}<br>
[[File:Animation M02 GIS 001 02.gif]]<br>
</ol>
<br>