The ARR to TUFLOW utility has been developed to help users set up a TUFLOW model that uses Australian Rainfall and Runoff (ARR) input parameters and the Australian Bureau of Meteorology (BOM) rainfall by automating the collection and processing of the data. The inputs and outputs of the tool are explained in detail below. '''''Note:''''' this tool helps with data processing, however is not a substitute to reading ARR. Similarly this wiki page discusses the use of the tool and the options, however context should be derived from ARR directly. Please see the [https://arr.ga.gov.au/arr-guideline
__TOC__▼
<br>
▲__TOC__
=Getting Started=
===Installation===
Line 80 ⟶ 81:
=Additional Options=
===Climate Change===
Climate change options can be added by clicking on '''Edit''' under the climate change section. This opens up a table widget that the user can then add/remove climate change scenarios based on the guidance in ARR v4.2. Once a user adds a scenario (green plus), they can double click on the values to change them. For example, double clicking on SSP2-4.5 under the 'SSP' heading will show the available Shared Socioeconomic Pathway (SSP) options. Scenarios added in the table will be displayed in the climate change section (underneath the edit button). Note: each scenario name must be unique and generally the table widget will force unique names. The scenario names will be used throughout the outputs and the user is free to customise the scenario names as they want.<br>
The table columns within the table widget are based on ARR guidelines v4.2 and the examples presented in Book 1, Chapter 6. Please note the following assumptions:<br>
Line 97 ⟶ 98:
** ''<scen_name>_rainfall_depths.csv''
** ''<scen_name>_losses.csv''<br><br>
[[File:
[[File: ARR_example_climate_change_rf_inflow_01a.png|1200px]] <br><br>
[[File: ARR_example_climate_change_tef_01a.png]]
Line 126 ⟶ 127:
===Rainfall Losses===
The following sections summarise the available loss options. Please note, as recommended in ARR2019, <u>[https://data.arr-software.org/ ARR datahub]</u> losses are only intended for rural use. They are not for direct use in urban areas. Furthermore, applications in New South Wales and Victoria should consider the following jurisdiction specific guidance:
''Since version v3.5 initial loss for durations greater than 72 hrs is assumed to be the same as the initial loss for 72 hrs. Previous to this version, these losses were output as zeros.''<Br>▼
* <u>[https://data.arr-software.org/nsw_specific NSW Specific Guidance]</u>
* <u>[https://data.arr-software.org/vic_specific VIC Specific Guidance]</u>
▲''Note: Since version v3.5 initial loss for durations greater than 72 hrs is assumed to be the same as the initial loss for 72 hrs. Previous to this version, these losses were output as zeros.''<Br>
=====Probability Neutral Losses=====
Probability neutral losses can be toggled on / off in the dialog (default is on). If 'on', this option will use probability neutral losses for the design burst initial loss rather than using the storm initial loss and pre-burst depths. If probability neutral losses are not available in the catchment area, then the method will automatically revert to using the storm initial loss). Currently this option cannot be used in conjunction with the '''complete storm''' option.<br><br>
Line 185 ⟶ 191:
The user can choose to output the complete storm (preburst + design burst) rather than just the design burst by checking on the following option (please see ARR Book 2 Chapter 5 [Section 5.9.9] for more information):<br>
[[File: ARR_complete_storm_checkbox_01a.png]]<br>
The complete storm generated by the tool will be the preburst depth (from the '''Preburst percentile''' extracted from the datahub) plus the design burst. The user will be required to select a preburst temporal pattern from the options listed below. The options below have been included at the request of users and are not a direct reference to any specific methodology outline in ARR. If you would like to see another method included, please email
Currently the ARR to TUFLOW tool supports the following preburst temporal pattern methods:
* '''Constant Rate''' - This will apply the preburst depth equally over a given time period. The time period can be specified as an absolute time (either as minutes or hours) or proprotional to the design storm e.g. a proportional value of 0.5 will apply a 30 min preburst to a 1 hr storm and a 15 min preburst to a 30 min storm.
| |||